| In
2002 the trustees decided upon a three phase plan to improve the
centre and add to the infrastructure for the community.
The
first phase of our plans was to extend the centre with the addition
of 2 purpose built offices, the creation of access's and a disabled
toilet so that all in the community could benefit regardless of
ability, as well as improving the fabric of the centre by upgrading
the furnishings and disco lighting. Letting out of the additional
office space to the Plymouth Money Advice Group has created an
additional 5 jobs in the area. This was achieved in Dec 04.
The
total cost of this phase was £157,289, of this £78,610
was funded through the Plymouth SRB Partnership.
Phase 1 (before) |
Phase 1 (after) |
|
|
The
second stage of the project was the creation of a retail unit
in partnership with the Plymouth and South West Co-operative Society
Ltd.; this project was brought about due to the lack of infrastructure
in the area, and much needed local employment opportunities which
fit in with the demography of the area. The build programme began
in March 05 with the widening of the vehicular access from Poole
Park Road with the actual building works commencing in June 05
with completion in November 05. The store opened for trading on
26 November 2005 with 8 employees all from within the community.
Apart from the rent the community will benefit from a profit share
agreement with the Plymouth and Southwest Co-operative Society
where 25% of the profits from the store will be passed back to
the community through Tamar View thus ensuring the future sustainability
of the centre's work.
The
cost of this phase was £ 549,883, with the PSW Co-op contributing
£160,000 and the Plymouth SRB Partnership contributing £130,000.
Phase
2 |
Store Opening Ceremony |
|

Opening Ceremony Conducted by (L-R) Pat Patel, Val Newman
(Store Manager), Barbara Duer (Chair PSW Co-op), Alison
Seabeck (MP) & Douglas Fletcher (CEO PSW Co-op)
|
Tamar
View Community Complex Ltd has invested £79,195 in the 1st
Phase of the project and £259,833 in the 2nd Phase. Of
this £160K is in the form of a loan from Lloyds TSB, the
remainder coming from the centres own operating surplus.
The
third and final stage is to create a Neighbourhood Nursery for
up to 50 children and a Community Fitness Suite within the Lhyner
Building which has stood empty for sometime. Approval for planning
consent was received on 24th December 2005. The trustees are working
hard on securing funding to bring this project to
fruition
and
have already established links with a number of Childcare providers
in the city as well as other organisations in the city.
A
copy of the floor plan for the third phase can be viewed by clicking
this link: Phase
3 Floor Plan PDF
Our
longer term plans, within the next 5 years, include becoming a
grant making trust so that profits from the Community Business
and surplus revenue generated from the above projects, through
the charity, can be used to support other local community enterprises
and support the work of voluntary sector within our community,
thus empowering the community, to be responsible for its own environment;
as well as adding to the services and facilities available to
them and creating a sustainable community.
Barne
Barton has been described as the size of a town without the facilities
of a village. The retail unit project is the first steps
of visible regeneration much needed in the area, which has high
indices of deprivation, and will create much needed additional
employment opportunities within the community.
A
copy of our plan can be downloaded here:
Three Phase plan PDF
Why
is this project such a success?
Firstly it is through the help and support of organisations and
businesses such as Co-active (http://www.co-active.org.uk/)
and the South West Regional Development Agency (SWRDA) (http://www.southwestrda.org.uk/)
and the Plymouth SRB Partnership. These have helped us remain
focused and have guided us through
challenging
times and have
given us expert advice. We are grateful to these organisations
without whom we would not be where we are now.
Secondly it is through the dedication of the trustees who have
involved the local community at all levels listening to their
needs and providing where we can for these. We also take into
account the affordability of our facilities and have structured
our pricing policy accordingly. We have planned for each new project
and constantly revisit our business plan, looking at the impact
our decisions will have not only on our community but also our
supporters and funders; and through the prudent use of our combined
resource; which includes our time as well as the centres finances
and facilities. We aim to make each pound of funding benefit the
community not only during the funding period, but for many years
afterwards.
By
using a professional business approach to a charitable cause we
have managed to do this and are putting the foundations in place
from which our community will benefit for many years to come.
|